British Airways

Project:
British Airways
Value:
£300,000 (to date)
Duration
3 Year Framework
Nature:
Asbestos Removal
Client:
British Airways

About the Project

London Heathrow Operations Base is held by British Airways (BA), occupies an area of approximately 74 Hectares and is located on the east side of the airport complex. The current use of the Base is for the client’s engineering planned and casualty maintenance facility, along Training and Administrative functions.

In March 2018 Decontaminate UK limited secured the three year Framework for Asbestos Removal, working alongside the clients external consultants CBRE (Maintenance), Turner & Townsend (Commercial) and RPS (Asbestos) to deliver the required Planned, Reactive and Emergency works, with projects valued in accordance with the agreed Schedule of Rates, and delivered in accordance with site specific KPI’s.

Since the commencement of the Framework Agreement we have undertaken asbestos removal works throughout the Operations Base, within BA properties in close proximity to Heathrow, and at Gatwick Airport. To date works have ranged in complexity and size, and have included the ‘hand-picking’ of asbestos debris from contaminated soils, the removal of asbestos based cladding, the removal of asbestos lined doors and partitioning, the removal of pigeon guano, and the decontamination
of high level gantries with Maintenance Hangars; under this Framework Decontaminate UK Limited act as Principal Contractor, and as such undertook all of the required PC duties most especially the safe integration and management of third-party contractors and their staff i.e. Scaffold and Access provision.

Project Challenges

With the predominant asbestos removal works being within facilities that operate on a 24 hour basis it is incumbent upon us to ensure that we maintain extensive numbers of site experienced personnel, and that in the event of an emergency we can have personnel, plant and materials on site within 2 hours of a call out.

The Operations Base, and its location within the boundary of Heathrow Airport, means that an extensive vetting system is in place to ensure that all persons able to access the facility are in possession of an ‘air-side’ security pass and as such this requires our staff to be in possession of security clearance that allows them to work within security sensitive environments.