Project:
Prime Retail Development In The West End
Value:
£48,500.00
Duration
6 Weeks
Nature:
Asbestos Removal
Client:
Knight Harwood

About the Project

Knight Harwood were appointed as Main Contractor for the refurbishment of this grade 2 listed building located within a popular retail area in London’s West End. Asbestos surveys and a specification of works was provided to Decontaminate for the removal of asbestos insulation board and asbestos insulation board debris along with two safes that has asbestos in their construction. Logistics were tight on this site which necessitated the use of modular decontamination facilities and wait and load collection for asbestos waste. The Decontaminate team safely completed the asbestos abatement works in accordance with the clients programme.

 

Materials removed:

- Asbestos insulation board

- Asbestos insulation board debris

- Asbestos cloth

- Asbestos containing safes

Project Challenges

- Working in a listed building

- Deliveries and collections to site

- Waste disposal in an area that is busy 24/7

- Manual handling of safes